Rabbit Run Combined Sewer Overflow (CSO)

Wilhelm > Wilhelm Portfolio > Water / Wastewater > Rabbit Run Combined Sewer Overflow (CSO)

Board of Public Works & Safety, City of Huntington

Huntington, IN

This guaranteed savings project provides temporary storage of wet weather flow in compliance with the City’s CSO Long Term Control Plan.

The project consists of constructing a two million gallon, cast-in-place concrete structure approximately 40 feet below grade. Other improvements consist of new screening equipment, pump improvements, and electrical/controls upgrades. Prior to entering into a contract with the City, the project team was able to reduce the construction costs by over $700,000 through initial value engineering.


SHARE Rabbit Run Combined Sewer Overflow (CSO)